Background

The Central California Clean Energy Transmission Project (C3ETP) is a planning effort to increase transmission capacity between northern and southern California. Project scope of the main alternative, proposed by PG&E, is to construct a new 500 kV double circuit tower line (DCTL) from Midway to a new Substation east of Fresno on new right-of-way. In this planning effort, a number of alternatives – including the one above-mentioned – are studied.

The project objectives are as follows:
    - Enhance reliability to Yosemite/Fresno area
    - Increase utilization of the Helms PSP to enhance the value of off-peak generation
    - Facilitate efficient management of renewables
    - Increase Path 15 transfer capability by ~1,250 MW
    - Provide opportunity for future expansion

Outcome
Pending closure of initiative

Process

Relevant Market Notices

Comments on C3ETP Fifth Stakeholder Meeting 21-Oct-2008

CPUC Comments on C3ETP Fifth Stakeholder Meeting 21-OCt-2008
pdf 34K | Abstract | 11/21/2008 15:55
TURN Comments on C3ETP Fifth Stakeholder Meeting 21-Oct-2008
pdf 17K | Abstract | 11/21/2008 15:56

C3ETP Fifth Stakeholder Meeting (Conference Call) 21-Oct-2008

Agenda - C3ETP Stakeholder Meeting (Conference Call) 21-Oct-2008
pdf 20K | Abstract | 10/17/2008 17:13
C3ETP Draft Preliminary Report
pdf 1432K | Abstract | 10/17/2008 17:35
3.1.1 Attachment 1 Load and Generation
pdf 41K | Abstract | 10/17/2008 17:40
3.1.1 PGE Greater Fresno Area Load Serving Capability Study2
pdf 48K | Abstract | 10/17/2008 17:39
3.1.1 Attachment-2 post-transient power flow analysis
pdf 259K | Abstract | 10/17/2008 17:41
3.1.1 Attachment-3 V-Q Analysis
pdf 537K | Abstract | 10/17/2008 17:42
3.1.1 Attachment-4 Dynamic Analysis
pdf 687K | Abstract | 10/21/2008 13:14
3.1.2 Helms PSP Pumping Operation
pdf 49K | Abstract | 10/17/2008 17:45
3.2 C3ETP Report skeleton v5
pdf 85K | Abstract | 10/17/2008 17:46
3.2.1 worst voltage violation plot 1
pdf 193K | Abstract | 10/20/2008 10:26
Presentation - SCE Reliability Assessment Status 21-Oct-2008
pdf 247K | Abstract | 10/17/2008 17:15
Presentation - PG&E Reliability Assessment Status 21-Oct-2008
pdf 701K | Abstract | 10/20/2008 16:27
Presentation - C3ETP Economic Assessment Dry-Run 21-Oct-2008
pdf 976K | Abstract | 10/17/2008 17:17

Comments on C3ETP Fourth Stakeholder Meeting 01-Aug-2008

BAMx Comments on C3ETP Fourth Stakeholder Meeting 01-Aug-2008
pdf 26K | Abstract | 09/18/2008 15:31
CPUC Comments on C3ETP Fourth Stakeholder Meeting 01-Aug-2008
pdf 49K | Abstract | 09/18/2008 15:33
TURN Comments on C3ETP Fourth Stakeholder Meeting 01-Aug-2008
pdf 27K | Abstract | 09/18/2008 15:34

Residents Comments on C3ETP Project (February - November 2008)

Charles Ashley Comments on C3ETP 21-Oct-2008
pdf 19K | Abstract | 11/21/2008 15:59
Jay Hinshaw Comments on C3ETP 21-Oct-2008
pdf 9K | Abstract | 11/21/2008 16:02
Rhonda Beebe Comments on C3ETP 21-Oct-2008
pdf 9K | Abstract | 11/21/2008 16:47
Ron Dickerson Comments (No. 1) on C3ETP 21-Oct-2008
pdf 21K | Abstract | 11/21/2008 16:00
Ron Dickerson Comments (No. 2) on C3ETP 21-Oct-2008
pdf 13K | Abstract | 11/21/2008 16:01
Larry and Jill Francis Comments on C3ETP 20-Aug-2008
pdf 9K | Abstract | 09/18/2008 14:26
Bill and Lynn Yeager Comments on C3ETP 16-Aug-2008
pdf 11K | Abstract | 09/18/2008 13:56
Greg Porterfield Comments on C3ETP 14-Aug-2008
pdf 11K | Abstract | 09/18/2008 14:04
Helen Shaw Comments on C3ETP 13-Aug-2008
pdf 9K | Abstract | 09/18/2008 14:05
Kathryn J. Biacindo Comments on C3ETP 13-Aug-2008
pdf 9K | Abstract | 09/18/2008 14:23
Robert Reed Comments on C3ETP 13-Aug-2008
pdf 8K | Abstract | 09/18/2008 15:15
Ron Dickerson Comments on C3ETP 13-Aug-2008
pdf 11K | Abstract | 09/18/2008 15:17
Barbara Hryniewicz Comments on C3ETP 12-Aug-2008
pdf 9K | Abstract | 09/18/2008 13:52
Carmen Grant Comments on C3ETP 12-Aug-2008
pdf 9K | Abstract | 09/18/2008 13:57
Chris Holland Comments on C3ETP 12-Aug-2008
pdf 9K | Abstract | 09/18/2008 13:59
Donna Patterson Comments on C3ETP 12-Aug-2008
pdf 10K | Abstract | 09/18/2008 14:00
Ed Kennedy Comments on C3ETP 12-Aug-2008
pdf 9K | Abstract | 09/18/2008 14:02
Jonna Patterson Comments on C3ETP 12-Aug-2008
pdf 41K | Abstract | 09/18/2008 14:07
Julie Yetko Comments on C3ETP 12-Aug-2008
pdf 9K | Abstract | 09/18/2008 14:08
Nathan Whittington Comments on C3ETP 12-Aug-2008
pdf 9K | Abstract | 09/18/2008 14:27
Rascon and Corral Comments on C3ETP 12-Aug-2008
pdf 9K | Abstract | 09/18/2008 14:29
Rhonda Beebe Comments on C3ETP 12-Aug-2008
pdf 9K | Abstract | 09/18/2008 15:14
Bill and Lynn Yeager Comments on C3ETP 02-Aug-2008
pdf 12K | Abstract | 09/18/2008 13:54
Ron Dickerson Comments on C3ETP 21-Jun-2008
pdf 12K | Abstract | 08/12/2008 13:59
Ron Dickerson Comments on C3ETP 09-Jun-2008
pdf 18K | Abstract | 08/12/2008 13:58
Charles Ashley Comments on C3ETP 21-May-2008
pdf 30K | Abstract | 05/21/2008 15:34
Ron Dickerson Comments on C3ETP 21-May-2008
pdf 14K | Abstract | 05/21/2008 15:36
Ron Dickerson Comments on C3ETP 16-Apr-2008
pdf 18K | Abstract | 04/16/2008 11:42
David Ayers and Carol Ayers Comments on C3ETP 11-Mar-2008
pdf 13K | Abstract | 04/16/2008 11:40
David Ayers Comments on C3ETP 29-Feb-2008
pdf 10K | Abstract | 04/16/2008 11:38
Carol Ayers Comments on C3ETP 27-Feb-2008
pdf 10K | Abstract | 04/16/2008 11:35

C3ETP Stakeholder Comments Matrix August 2008

C3ETP Stakeholder Comments Matrix August 2008
pdf 78K | Abstract | 08/13/2008 10:12

C3ETP Fourth Stakeholder Meeting (Conference Call) 01-Aug-2008

Agenda - C3ETP Stakeholder Meeting (Conference Call) 01-Aug-2008
pdf 20K | Abstract | 08/01/2008 09:26
C3ETP Study Plan
pdf 1131K | Abstract | 07/25/2008 11:55
Presentation - C3ETP Introduction 01-Aug-2008
pdf 165K | Abstract | 07/30/2008 18:29
Presentation - C3ETP Economic Study Plan 01-Aug-2008
pdf 400K | Abstract | 07/30/2008 18:30
Presentation - Discussion on Economic Assessment 01-Aug-2008
pdf 276K | Abstract | 07/30/2008 18:32
Presentation - PG&E Reliability Assessment Status 01-Aug-2008
pdf 350K | Abstract | 07/30/2008 18:33

C3ETP Third Stakeholder Meeting 24-Apr-2008

Agenda - C3ETP Third Stakeholder Meeting 24-Apr-2008
pdf 29K | Abstract | 04/22/2008 08:52
Presentation - Study Overview 24-Apr-2008
pdf 479K | Abstract | 04/22/2008 13:29
Presentation - CAISO Observations on Preliminary Reliability Analyses 24-Apr-2008
pdf 233K | Abstract | 05/07/2008 15:54
Presentation - PG&E Reliability Assessment 24-Apr-2008
pdf 836K | Abstract | 04/22/2008 13:26
Presentation - SCE Reliability Assessment 24-Apr-2008
pdf 389K | Abstract | 04/22/2008 13:19
Presentation - Economic Assessment Status and Next Steps 24-Apr-2008
pdf 321K | Abstract | 04/22/2008 13:22

C3ETP - SCE Study Plan

C3ETP - SCE Study Plan
pdf 189K | Abstract | 03/05/2008 15:44

C3ETP - PG&E Study Plan

C3ETP - PG&E Final Study Plan 29-Feb-2008
pdf 882K | Abstract | 02/29/2008 15:19
C3ETP - PG&E Preliminary Study Plan 06-Feb-2008
doc 2073K | Abstract | 01/31/2008 15:15
C3ETP - PG&E Preliminary Study Plan 09-Jan-2008
pdf 166K | Abstract | 01/08/2008 13:56

C3ETP Second Stakeholder Meeting 06-Feb-2008

Agenda - C3ETP Stakeholder Meeting 06-Feb-2008
pdf 38K | Abstract | 01/30/2008 16:06
Presentation - C3ETP Introduction 06-Feb-2008
pdf 350K | Abstract | 01/30/2008 16:36
Presentation - C3ETP Stakeholder Comments 06-Feb-2008
pdf 233K | Abstract | 02/01/2008 15:54
Presentation - C3ETP Scope of the Planning Study 06-Feb-2008
pdf 1187K | Abstract | 02/01/2008 15:45
Presentation - C3ETP Reliability Assessment 06-Feb-2008
pdf 183K | Abstract | 01/30/2008 16:38
Presentation - C3ETP Economic Assessment 06-Feb-2008
pdf 603K | Abstract | 02/01/2008 15:46
C3ETP - PG&E Study Plan 06-Feb-2008
doc 2073K | Abstract | 01/31/2008 15:15

Stakeholder Comments on C3ETP Preliminary Planning Study 06-Feb-2008


CalWEA Comments on the C3ETP Draft Study Plan 06-Feb-2008
pdf 25K | Abstract | 02/26/2008 10:38
KRCD Comments on the C3ETP Draft Study Plan 06-Feb-2008
pdf 9K | Abstract | 02/26/2008 10:40
SCE Comments on the C3ETP Draft Study Plan 06-Feb-2008
pdf 10K | Abstract | 02/26/2008 11:06
Watts Valley Preservation Society Comments on the C3ETP Draft Study Plan 06-Feb-2008
pdf 14K | Abstract | 02/26/2008 11:14

C3ETP First Stakeholder Meeting 09-Jan-2008

Agenda - C3ETP Stakeholder Meeting 09-Jan-2008
pdf 28K | Abstract | 01/02/2008 15:38
Presentation - C3ETP Introduction 09-Jan-2008
pdf 638K | Abstract | 01/08/2008 08:46
Presentation - C3ETP Study Plan 09-Jan-2008
Revised Slide 16, "5: Midway - E2 230 kV SCTL" changed to "5: Midway - E2 230 kV DCTL".
pdf 3237K | Abstract | 01/10/2008 15:28
Presentation - C3ETP Reliability Assessment 09-Jan-2008
pdf 284K | Abstract | 01/08/2008 08:48
Presentation - C3ETP Economic Assessment 09-Jan-2008
pdf 1455K | Abstract | 01/08/2008 08:56
Central California Clean Energy Transmission Project (C3ETP) PG&E Study Plan 09-Jan-2008
pdf 166K | Abstract | 01/08/2008 13:56

Stakeholder Comments on C3ETP Preliminary Planning Study 09-Jan-2008

CalWEA Comments on the C3ETP Draft Study Plan 09-Jan-2008
pdf 12K | Abstract | 01/28/2008 15:43
CEC Comments on the C3ETP Draft Study Plan 09-Jan-2008
pdf 22K | Abstract | 01/29/2008 12:42
SCE Comments on the C3ETP Draft Study Plan 09-Jan-2008
pdf 22K | Abstract | 01/28/2008 15:45
Susan Schneider Comments on the C3ETP Draft Study Plan 09-Jan-2008
pdf 10K | Abstract | 01/28/2008 15:48

© 2005 -  California ISO
All Rights Reserved
Sitemap  Privacy Policy  Legal Notice  Tell Us What You Think